Risk / Uncertainty In SEER and Project Management
The question was asked “what probability should I estimate at” The answer follows: Risk is really uncertainty. So the question becomes how much uncertainty can or should I allow in my project plans. There are many approaches to this, depending on circumstances including:
What are the consequences of an overrun: Many large military type programs in the US budget at a 70% or 80% probability. These kinds of programs are generally large and not well defined at the early planning stages. They use the higher probability so they don’t have to go back for more budget or schedule as the program progresses. These programs will generally manage to a 50% probability, using the overage as a buffer for program growth.
Is The Project Fixed Price: Many programs that must bid on programs at fixed price will initially estimate at a probability like 80% so that they are covered if the project becomes more complicated than their initial looks. Of course competitive issues may cause them to bid lower.
Is this an in house Project: Many projects will plan at a 50% (most likely) probability. This allows them to have a tough but achievable plan and if the project runs into difficulty they can adjust.
I recommend managing to the 50% probability… Tough but achievable schedule and effort.
Some projects Estimate at the 20% Probability: This is a lower cost / schedule plan that can win a contract. Unfortunately these projects usually overrun. But they have taken calculated risks.
I once heard of a program that was thrilled that the 1% probability met with their hopes for the program. So they had a plan with a 99% probability of failure.
Â
Thank you for reading “Dan on Estimating”, if you would like more information about Galorath’s estimation models, please visit our contact page or call us at +1 310 414-3222.
Related posts:
- Estimating Best Practices The following are the bullet points from Dan’s paper on estimating best practices. Â Using these best practices can increase project...
- Don’t Hide Uncertainty: Measure It We all need to deal with estimates / projections for the future. When doing so, it is essential to include...
- NPD 1000.5 NASA Cost-Risk Directive Just about hot off the presses (January 2009) is NASA’s cost risk directive. The directive defines many things with potentially...
- Estimating Project Risk Using Scenarios (Without Monte Carlo) I was at a costing syposium today where Paul Garvey of Mitre gave a talk on doing risk analysis without...
- Viable Software Estimation Modeling: A Key Component Of Software Risk Management I spoke with someone recently who explained the reason they use SEER is for risk management. They pointed out that...
Comments
One Response to “Risk / Uncertainty In SEER and Project Management”
Leave a Reply



Current AF Cost Analysis Agency recommended practice is to budget to the mean and identify risk dollars and schedule. This represents a shift from the not-to-distant past of trying to budget to 80%CL.