Standard WBS For Space System Cost Estimating

The NRO cost group provided a Work Breakdown Structure (WBS) for costing their projects. As quoted from the introduction:

The standard WBS was developed to capture the costs of any NRO program, whether it is an operational space program, technology demonstration program, ground station upgrade, or a system of systems. It is structured to accommodate varying levels of detail in available data. This allows data to be reported at either lower levels or at higher levels, if lower level data are not available. The wide range of system engineering, integration and test, and program management levels within the WBS is a prime example of how data are reported at many different levels within a program. The standard WBS is designed to allow data reporting at whatever level they are recorded. Because of this versatility, some WBS elements may be repeated, such as the case of a satellite system that operates with two ground stations. For this situation, the costs for each ground station are reported separately via WBS elements 1.3a and 1.3b, and all lower level elements for each ground station will sum up to their respective ground station. The same scheme applies to multiple and dissimilar spacecraft within a program, which will be reported separately as “spacecraft a” and “spacecraft b”. Thus, there may be a number of elements in the standard WBS that are irrelevant to any individual program, but are necessary for the database structure to account for a varying level of cost data on disparate legacy programs. If cost data are sparse, they still may be mapped into appropriate higher levels of the WBS”

And as Bryn pointed out: another one from OSD The OSD CAIG also has a mandatory cost and software reporting for specified programs – basically the big ones (DoD 5000-04-M-1, April 18 2007) – with a reference to mandatory WBS structure (Data Item Description DI-MGMT-81334, “Contract Work Breakdown Structure,”
current version).  More info available at http://dcarc.pae.osd.mil



Thank you for reading “Dan on Estimating”, if you would like more information about Galorath’s estimation models, please visit our contact page or call us at +1 310 414-3222.

Related posts:

  1. Guidelines and Metrics for Assessing Space System Cost Estimates I recently saw a presentation by Bernie Fox of Rand regarding guidelines and metrics for assessing space system cost estimates.  Very...
  2. GAO Cost Estimating and Assessment Guide Released Congratulations to the GAO team for releasing the “Cost Estimating and Assessment guide: Best Practices for developing and Managing Capital...
  3. Towards a Standard Definition of IT Infrastruture In the article “IT Policy: An Essential Element of IT Infrastructure“  the authors correctly state that IT Infrastructure is more...
  4. Estimating Best Practices The following are the bullet points from Dan’s paper on estimating best practices.  Using these best practices can increase project...
  5. Cost Readiness Level (CRL) Establishing Cost Risk Based On Engineering Decisions I am working on a paper for NASA’s project manager conference.  In the course of this work I again reviewed...

Comments

3 Responses to “Standard WBS For Space System Cost Estimating”

  1. Dr. Paul D. Giammalvo on February 17th, 2009 4:49 am

    Hi Dan,
    I am very keen to learn more about ANY standardized WBS that might apply or be adaptable to the telecom sector. Is this a proprietary model or has it been put into the public domain? Can I get a copy for academic purposes?

    Many thanks!!!

    Dr. PDG, Jakarta

  2. Bryn on February 17th, 2009 8:22 am

    The OSD CAIG also has a mandatory cost and software reporting for specified programs – basically the big ones (DoD 5000-04-M-1, April 18 2007) – with a reference to mandatory WBS structure (Data Item Description DI-MGMT-81334, “Contract Work Breakdown Structure,”
    current version). More info available at http://dcarc.pae.osd.mil.

  3. Jonathan Serna on April 9th, 2011 7:22 pm

    Hi,

    Can I ask what is the standard percentage of the ff;
    Labor cost – ?%
    Profit cost – ?%
    Consumables – ?%
    Overhead – ?%
    for installation of pipes and ducts
    Thank you.