Step Two: Establish Technical Baseline, Ground Rules, and Assumptions

Establish Technical Baseline, Ground Rules, and Assumptions

To establish an accurate technical baseline, you must first define the functionality that must be estimated. Recognize the constraints associated with the application and the project, and determine what functionality must be developed versus what can be provided via COTS or reuse.

Ground rules are concise statements that describe the basis from which the estimate is made. “This estimate includes functions a, b, and c only; no costs associated with travel are included” is an example of a ground rule.

Assumptions are suppositions that describe unknown variables that will affect an estimate. “This estimate assumes the software developer will use development system X” is an example of an assumption. Later in the project when you confirm that “development system X” will be employed, this proven assumption would then be restated as a ground rule.

Ground rules and assumptions form the foundation of the estimate and, although in the early stages of the estimate they are preliminary and therefore rife with uncertainty, they must be credible and documented. Review and redefine these assumptions regularly as the estimate moves forward.

Previous:
Step One: Establish estimate scope

Coming Next:
Step Three: Collect Data



Thank you for reading “Dan on Estimating”, if you would like more information about Galorath’s estimation models, please visit our contact page or call us at +1 310 414-3222.

Related posts:

  1. Step One: Establish Estimate Scope and Purpose Establish Estimate Scope and Purpose Define and document expectations. When all participants understand the scope and purpose of the estimate,...
  2. Step Five: Prepare Baseline Estimate Budget and schedule are derived from estimates, so if an estimate is not accurate, the resulting schedules and budgets are...
  3. Ten-step Project Estimation Process Software Estimation Concepts Many project managers and project management offices have unrealistic expectations about estimates. The definition of the verb...
  4. Step Seven: Estimate Validation and Review Step Seven: Estimate Validation and Review At this point in the process, your estimate should already be reasonably good-but it...
  5. 10 Step Estimation Process Overview Viable estimation is critical to successful software projects whether it is agile, waterfall, or anything in-between. In the book “Software...

Comments

One Response to “Step Two: Establish Technical Baseline, Ground Rules, and Assumptions”

  1. Step One: Establish Estimate Scope and Purpose | Project Planning & Estimation on March 15th, 2009 12:07 pm

    [...] Coming Next: Step Two: Establish Technical Baseline, Ground Rules, and Assumptions [...]

Leave a Reply




CommentLuv badge